LIFFEY STREET PUBLIC REALM WORKS UPDATE
- Mon 27 March, 2023
Cairn Construction, the public works contractor for DCC has shared the PR circular for this fortnight which can be viewed here.
The Contractor will during the next two weeks focus on demobilising Workfront A and commence mobilisation at Workfront B on the lower half of Liffey Street Upper. The Contractor will commence and continue duct installations for Water, PL, Traffic, EIR & Virgin Media along LSU between Proby’s Lane and Middle Abbey Street.