Liffey Street Public Realm Works Update

  • Fri 26 January, 2024

Cairn Construction, the public works contractor for DCC has shared the PR circular for this fortnight which can be viewed here.

For the next two weeks the contractor will focus on completing west side footpath to south end of ‘Motel One’, continuing to effective completion of the carriageway setts-paving, and all with a view to moving to the west-side footpath (opposite Motel One) with a view to excavation and new re-paving with granite. Public Lighting wall mounted brackets install will also commence. Works on Liffey Street Lower are suspended until new granite material arrives.

For further information, contact info@cairn.ie